To obtain a permit to
install an OSSF, the following information must be submitted to the Health
District.
-
Completed BCPHD
Application showing legal information about the owner, the property,
proposed construction, and professionals involved in the planning and
installation process
-
Prepared site
evaluation completed by a licensed site evaluator or a professional engineer
-
Appropriate design
based on above information; OSSFs requiring professional designs must be
prepared by a qualified P.E. or R.S.
-
Maintenance
contracts or affidavits, if required
-
Appropriate fee
-
Standard system
without professional design - $250
-
Standard system
with professional design - $350
-
Any system with
professional design - $325 (excludes Aerobic Treatment)
-
Aerobic system
requiring maintenance contract $450
The Health District will review the above information to insure the submitted
material is complete and to ensure an acceptable OSSF application is submitted.
The application submitted will be evaluated based upon the technical information
and site evaluation . The permit to install will be issued once a review
confirms compliance with the approved local order. Construction of an OSSF can not begin until a permit is issued. The permit is to
construct the design approved. Altering the construction of the approved
design is a violation of OSSF rules.
Inspection are
scheduled by calling the Health District at:
Temple Office - (254)778-7557
Killeen Office - (254)526-3197